    "id": "COL-001",
    "project": "US-COL2",
    "claim": "公司披露兩批叢集約 210／220 MW compute power，工期 91／64 天。",
    "event": null,
    "sources": [
      "S01"
    ],
    "status": "公司披露；非獨立驗收",
    "boundary": "兩批叢集；不可等同整座電廠工期或全場實測 IT 負載。",
    "next": "取得分期驗收與計量定義。"
  },
  {
    "id": "COL-002",
    "project": "US-COL2",
    "claim": "MDEQ 資料庫列施工許可 0680-00119 於 2026-03-11 核發。",
    "event": "2026-03-11",
    "sources": [
      "S03"
    ],
    "status": "主管機關紀錄",
    "boundary": "Southaven；施工許可不等於送電或運轉驗收。",
    "next": "取得完整許可及後續履行文件。"
  },
  {
    "id": "COL-003",
    "project": "US-COL2",
    "claim": "八月官方議程摘要記錄最多 69 部臨時機組、依 Appendix A 停止操作及雙週申報；九月另列修正摘要。",
    "event": "2026-08／2026-09（議程）",
    "sources": [
      "S19",
      "S20"
    ],
    "status": "官方摘要；依來源稽核紀錄",
    "boundary": "未取得現行完整命令與附錄，精確期限、逐台現況及履行均未知。",
    "next": "核對七月原件、九月修正案、完整 Appendix A 與履行序列。"
  },
  {
    "id": "COL-004",
    "project": "US-COL2",
    "claim": "公司公布 1.2 GW／41 部永久機組方案。",
    "event": "2026-07-30（公告）",
    "sources": [
      "S02"
    ],
    "status": "公司披露",
    "boundary": "規劃容量，非可交付 IT 容量。",
    "next": "取得分期試運轉與淨輸出。"
  },
  {
    "id": "COL-005",
    "project": "US-COL2",
    "claim": "完整跨州電氣拓樸尚未核實。",
    "event": null,
    "sources": [
      "S01",
      "S02"
    ],
    "status": "本次取得範圍的限制",
    "boundary": "取代舊稿確定的短距離跨州輸電敘述；不代表線路不存在。",
    "next": "單線圖、竣工、計量及供電責任文件。"
  },
  {
    "id": "ORA-001",
    "project": "US-JUPITER",
    "claim": "Oracle 公告 Jupiter 最高 2.45 GW 燃料電池裝置方案。",
    "event": "2026-04-27（公告）",
    "sources": [
      "S05"
    ],
    "status": "公司披露",
    "boundary": "最高規劃裝置值，非已營運 IT MW。",
    "next": "分期交付與驗收資料。"
  },
  {
    "id": "ORA-002",
    "project": "US-JUPITER",
    "claim": "Certarus 的 Utah 60 MW 公告未具名 Oracle；TNW 稱 Jupiter 考慮卡車供氣。",
    "event": null,
    "sources": [
      "S06",
      "S07"
    ],
    "status": "供應商披露／媒體轉述",
    "boundary": "分開 Utah、Texas、Jupiter；未確認 Jupiter 已部署。",
    "next": "客戶、場址與供氣啟用的一手確認。"
  },
  {
    "id": "ORA-003",
    "project": "US-JUPITER",
    "claim": "媒體報導管線投運目標由 2026-08-15 延至 2027-02-01。",
    "event": "2026-08-15 → 2027-02-01（目標）",
    "sources": [
      "S08"
    ],
    "status": "媒體轉述；原申報待取",
    "boundary": "170 天為日期差，非資料中心損失服務天數。",
    "next": "取得 Transwestern／FERC 原文件。"
  },
  {
    "id": "MOD-001",
    "project": "MOD-BRIDGE-FUEL",
    "claim": "新聞四倍氣價的分母為樞紐價；A、B 改作獨立送達價假設。",
    "event": null,
    "sources": [
      "S07",
      "S09"
    ],
    "status": "分母修正／模型假設",
    "boundary": "HHV 60% 效率與全部氣價皆是假設；只算燃料費。",
    "next": "取得同日同場址的可比報價與設備性能。"
  },
  {
    "id": "MOD-002",
    "project": "MOD-COL-THRESHOLD",
    "claim": "以可重算的每月貢獻門檻取代實際報酬語氣。",
    "event": null,
    "sources": [],
    "status": "研究者模型",
    "boundary": "430 MW 為假設 IT 尺度；無實際收入、成本或風險調整 NPV。",
    "next": "取得增量成本與可歸因效益。"
  },
  {
    "id": "CN-001",
    "project": "CN-NOTE-01",
    "claim": "SemiAnalysis 公開部分提出零售閒置與新 AI 批發需求並存的觀察。",
    "event": null,
    "sources": [
      "S10"
    ],
    "status": "作者觀察；付費文章的免費預覽",
    "boundary": "只讀原站免費預覽；未讀付費正文、未獨立驗證全國容量及底層模型。",
    "next": "以可識別場址與用途交叉核對。"
  },
  {
    "id": "CN-002",
    "project": "CN-NOTE-01",
    "claim": "VNET 披露批發在役 1,007 MW、使用 744 MW、承諾 970 MW；零售使用率 64.5%。",
    "event": "2026-06-30",
    "sources": [
      "S11"
    ],
    "status": "公司披露／未經審計",
    "boundary": "公司層級；批發 MW 與零售機櫃分開；非 GPU 利用率或全國統計。",
    "next": "場址、客戶用途及設備使用證據。"
  },
  {
    "id": "CN-003",
    "project": "CN-NOTE-01",
    "claim": "歷史政策將跨區調度與綠色電力協同列為工作方向。",
    "event": null,
    "sources": [
      "S12"
    ],
    "status": "政策原文",
    "boundary": "政策目標不是成果；未完成後續政策與地方執行查核。",
    "next": "取得案場採購、選址及執行紀錄。"
  },
  {
    "id": "CN-004",
    "project": "CN-NOTE-01",
    "claim": "技術摘要提供記憶體、運算、互連與軟硬體協同的研究切入點。",
    "event": null,
    "sources": [
      "S13"
    ],
    "status": "作者摘要",
    "boundary": "未閱讀全文；不可外推全中國有效算力。",
    "next": "全文、可比工作負載與實測資料。"
  },
  {
    "id": "COL-006",
    "project": "US-COL2",
    "claim": "逐台退役與移除實績尚未由官方同件核實。",
    "event": null,
    "sources": [],
    "status": "撤回舊具體說法；未知",
    "boundary": "原第三方信件未完成官方版本對照，不作現行證據。",
    "next": "取得官方往返信件、設備對照及後續履行／驗收紀錄。"
  },
  {
    "id": "COL-007",
    "project": "US-COL2",
    "claim": "分期設備啟動、分類與驗收狀態尚未由官方同件核實。",
    "event": null,
    "sources": [],
    "status": "撤回舊具體說法；未知",
    "boundary": "原第三方信件未完成官方版本對照，不作現行證據。",
    "next": "取得官方往返信件、設備對照及後續履行／驗收紀錄。"
  },
  {
    "id": "CN-005",
    "project": "CN-CAND-01",
    "claim": "VNET 披露截至 2026-06-30，公司批發在建容量為 585 MW。",
    "event": "2026-06-30",
    "sources": [
      "S11"
    ],
    "status": "公司披露／未經審計",
    "boundary": "公司在建總量；不代表未來 12 個月交付，也未證實大部分來自烏蘭察布。",
    "next": "取得可讀電話稿並核對園址、期別與交付節點。"
  },
  {
    "id": "CN-006",
    "project": "CN-CAND-02／CN-CAND-03",
    "claim": "GDS 2Q26 新建訂單列烏蘭察布70 MW、韶關83 MW。",
    "event": "2026年第二季",
    "sources": [
      "S17"
    ],
    "status": "公司訂單披露",
    "boundary": "Power／New Build bookings，excluding reservations；不是已送電、客戶驗收的 IT 負載或有效算力。",
    "next": "取得各訂單對應園址樓棟、交付日期、設備與工作負載。"
  },
  {
    "id": "CN-007",
    "project": "CN-CAND-03",
    "claim": "韶關主管機關6/15公告受理接入配套工程環評，表列受理日期6/12。",
    "event": "2026-06-12（受理）；2026-06-15（公告）",
    "sources": [
      "S18"
    ],
    "status": "主管機關受理紀錄",
    "boundary": "非批覆或送電，未核實與83 MW批次的映射。",
    "next": "取得環評批覆、接入協議、投運驗收及樓棟映射。"
  }
]